An ongoing record of mediocrity:
….critics say customers shouldn’t be on the hook for tens of millions of dollars in legal fees the utility incurred while fighting court cases before the plant was built, and a contractor dispute that arose during construction.
The extra $177.6 million for the power plant, tacked onto a price tag of $2.191 billion, is one of the key issues facing the state Public Service Commission as it weighs how much We Energies can raise electricity rates in January.